Santa Cruz Market Repairs
Awarded project with approval escalation, workforce demand, supplier order, invoice status, and evidence tasks.
Execution state
This is the awarded project workspace. It connects the accepted bid to approvals, supplier orders, workforce demand, evidence collection, invoices, Atlas conversations, and network coordination.
42%
St. Elizabeth
JMD 31M planning band
Milestone 1
Utility clearance escalated June 17
Project delivery dossier
The workspace should read like a live delivery file: what is being built, where it is happening, what milestone matters next, and which dependency blocks action.
42% toward milestone one
| Field | Visible value | Why it matters |
|---|---|---|
| Project | Santa Cruz Market Repairs | Primary awarded workstream the contractor is delivering. |
| Location | St. Elizabeth | Keeps workforce, supplier delivery, inspection, and evidence tied to the correct parish. |
| Budget signal | JMD 31M planning band | Frames invoice timing and delivery discipline without exposing private finance operations. |
| Current milestone | Milestone 1 | Defines what evidence must be gathered before payment review. |
| Active blocker | Utility clearance escalated June 17 | Shows the next project condition that needs human follow-up. |
Atlas project conversation
Open the project group in Atlas for supplier, agency, workforce, and contractor conversations tied to this workspace.
Project workstreams
Open the project-linked workstream you need next. Each route stays tied to the approved workspace record.
Project timeline
Contract accepted
Awarded bid has been accepted and workspace opened.
Utility clearance
JPS route clearance response is the current blocker before roof work can start.
Workforce mobilization
Santa Cruz crew demand requests fourteen roof, drainage, safety, and evidence roles through Atlas Jobs.
Material delivery
Mandeville Materials delivery targets roof sheets, fasteners, membrane, and sealants before the first work block.
Milestone evidence
Pre-work photos, inspection checklist, and material receipts required for invoice one.
Delivery gates before payment
These gates keep the project workspace practical: each one has an owner, a visible state, and a reason it affects mobilization or invoice readiness.
| Gate | Owner | Visible state |
|---|---|---|
| Approval path | Agency liaison | Utility clearance response pending |
| Workforce | Contractor admin | Shortlist ready for human review |
| Supplier delivery | Mandeville Materials | Delivery proof expected before first work block |
| Evidence | Site supervisor | Baseline photos and receipts required |
| Invoice readiness | Finance reviewer | Locked until inspection evidence is attached |
Project update
Add a project-safe update for the workspace. This records progress context only; it does not approve, publish, or pay anything.
Project workspace
This workspace connects the awarded bid to approvals, workforce, supplier coordination, evidence, invoices, and network rooms.
Current delivery focus
The immediate work is to clear utility access, prepare the roof crew shortlist, confirm material delivery, and assemble milestone evidence before invoice review.
Santa Cruz Market Repairs
BlueCrest Roofing & Civil Ltd.
Utility clearance escalated June 17
Mandeville Materials roofing order
Fourteen roof crew roles requested
Review workforce demand and supplier delivery timing