Bids
Submit bid packages, track statuses, amend bids, and review award outcomes.
Bid package
Santa Cruz Market Bid
Submitted package for the Santa Cruz Market RFP with proposal, estimate, team plan, timeline, and documents attached.
Submitted bid package under review
This bid has already been submitted. You can review the proposal, estimate, team, timeline, and documents, but a project workspace only unlocks after award and contract acceptance.
Santa Cruz Market submitted bid
Santa Cruz Market Repairs
Santa Cruz Market Repairs
St. Elizabeth
Step 1
Proposal
Step 2
Estimate
Step 3
Team
Step 4
Timeline
Step 5
Documents
Step 6
Review
Proposal narrative
BlueCrest proposes a staged roof and drainage recovery approach for Santa Cruz Market that protects vendor access, isolates work zones, and gives NaRRA inspection-ready evidence at each milestone. The proposal prioritizes weatherproofing, safe circulation, and clear handoff documentation.
Method
Staged demolition, replacement, waterproofing, and closeout by market block.
Quality control
Daily site photos, material receipts, supervisor sign-off, and inspection checklist.
Assumptions
Vendor access remains active with restricted zones and scheduled delivery windows.
Estimate and cost breakdown
Cost categories stay visible so reviewers can understand the bid basis.
Total estimate
JMD 31.5M
| Category | Basis | Amount |
|---|---|---|
| Labour | Roof crew, waterproofing technicians, safety marshal | JMD 9.8M |
| Materials | Roof sheets, ridge caps, flashing, fasteners, sealants | JMD 14.6M |
| Equipment | Scaffolding, lift support, disposal, transport | JMD 3.2M |
| Preliminaries | Site setup, access protection, permits, supervision | JMD 2.5M |
| Contingency | Weather and market-access staging allowance | JMD 1.4M |
Proposed team
Marsha Campbell
Project lead · Primary contractor admin
Devon Riley
Site supervisor · 12 years roof works
Alana Grant
Safety officer · Site safety and access control
Kemar Blake
Drainage lead · Minor civil works
Proposed timeline
Mobilization
3 daysSite handoff, vendor access plan, material staging
Roof replacement
10 daysSheeting, flashing, ridge caps, and gutter works
Drainage corrections
5 daysRunoff correction and minor civil repair
Inspection closeout
2 daysEvidence pack, punch list, handover photos
Bid documents
| Document | Purpose | Status | Action |
|---|---|---|---|
| Technical method statement | Shows staging, work method, and quality checks | Attached | View |
| Tax Compliance Certificate | Confirms contractor tax standing for procurement | Accepted | View |
| Company registration | Confirms legal business registration in Jamaica | Accepted | View |
| Authorized representative ID | Confirms the workspace owner and signatory | Accepted | View |
| Supplier quotation basis | Supports the material price assumptions | Attached | View |
Package review
Review consolidates the bid narrative, cost basis, team, timeline, and documents before submission or amendment. A project workspace is not available from this state unless NaRRA awards the bid and the contractor accepts the contract.
Proposal
Estimate
Team
Timeline
Documents
Review
Submitted package
The bid carries the contractor proposal, estimate, team plan, timeline, compliance documents, and supplier assumptions into review.
Review boundary
Register shows the contractor-facing submission status and any returned amendments. Evaluation notes, competitor submissions, and award decisions remain outside this workspace.
Santa Cruz Market submitted bid
Santa Cruz Market Repairs
Santa Cruz Market Repairs
St. Elizabeth
June 16, 2026
Under review
Review state
This bid is locked for procurement review. It can receive an award outcome, a written reason, or an amendment request, but it cannot become a project from this screen.